Justia Government Contracts Opinion Summaries

by
Several states challenged Executive Order 14026, which mandated a $15 minimum wage for federal contractors, and the Department of Labor (DOL) rule implementing it. The states argued that the executive order and the DOL rule violated the Federal Property and Administrative Services Act (FPASA) and the major questions doctrine, and that the DOL rule violated the Administrative Procedure Act (APA).The United States District Court for the District of Arizona dismissed the states' complaint and denied their request for a preliminary injunction. The district court concluded that the wage mandate did not violate the FPASA, the major questions doctrine did not apply, and the rule was not subject to arbitrary-or-capricious review under the APA because the DOL had to adopt the policy by executive order.The United States Court of Appeals for the Ninth Circuit reviewed the case and reversed the district court's dismissal of the complaint, vacated the denial of the preliminary injunction, and remanded for further proceedings. The Ninth Circuit held that the minimum wage mandate exceeded the authority granted to the President and DOL under the FPASA because the FPASA’s purpose statement does not authorize the President to impose a wage mandate without other operative language in the FPASA. The court also held that the major questions doctrine did not apply because the executive order was not a transformative expansion of authority. Finally, the court found that the DOL acted arbitrarily or capriciously by failing to consider alternatives to the $15 per hour minimum wage mandate, thus violating the APA. View "STATE OF NEBRASKA V. SU" on Justia Law

by
Sage Acquisitions LLC ("Sage") entered into contracts with the United States Department of Housing and Urban Development ("HUD") to provide management and marketing services for properties in HUD's Real Estate Owned ("REO") disposition program. Sage was awarded three contracts for different geographic areas. Sage filed claims with the HUD contracting officer for settlement costs due to the termination for convenience of the contracts, equitable adjustments for reduced property assignments, and damages for scope reduction. Sage also claimed damages for HUD's alleged breach of a contractual option provision and a related bridge contract.The Civilian Board of Contract Appeals ("Board") denied Sage's claims. The Board held that the contracts were Indefinite Delivery/Indefinite Quantity ("IDIQ") contracts, not requirements contracts, and that HUD had met its obligations by ordering the guaranteed minimum quantities. The Board also found that HUD did not breach the contracts by issuing six-month task orders instead of one-year orders and that HUD did not breach the bridge contract by using REO alternatives.The United States Court of Appeals for the Federal Circuit reviewed the case and affirmed the Board's decision. The court held that the contracts were indeed IDIQ contracts, as they explicitly stated and included guaranteed minimums. The court found that the language in the contracts did not confer exclusivity to Sage, and HUD's reservation of the right to work with other contractors was incompatible with a requirements contract. The court also held that HUD's issuance of six-month task orders was permissible under the contract terms. Finally, the court concluded that HUD did not breach the bridge contract, as Sage was aware of HUD's use of REO alternatives, and HUD's actions were based on legitimate business purposes. View "SAGE ACQUISITIONS LLC v. HUD " on Justia Law

by
The Boeing Company filed a complaint against the United States, challenging a contracting officer's decision that required Boeing to pay over $1 million due to changes in its cost accounting practices. Boeing argued that the government's demand violated the relevant Federal Acquisition Regulation (FAR) and Cost Accounting Standards (CAS) provisions, which should offset increased costs with decreased costs, resulting in no net increase. Boeing's complaint included three contract claims and an illegal exaction claim.The United States Court of Federal Claims dismissed Boeing's contract claims without prejudice, stating it lacked jurisdiction to review the validity of the regulation under the Administrative Procedure Act (APA). The court also dismissed the illegal exaction claim with prejudice, despite acknowledging jurisdiction, because it believed it lacked the authority to consider the claim under the Contract Disputes Act (CDA).The United States Court of Appeals for the Federal Circuit reversed the lower court's decision. The appellate court held that the Court of Federal Claims has jurisdiction under the CDA to resolve the contract dispute, including the validity of the underlying regulation. The court also held that the Court of Federal Claims has jurisdiction over Boeing's illegal exaction claim under the Tucker Act, 28 U.S.C. § 1491(a)(1), and that the CDA does not preclude this jurisdiction. The case was remanded for further proceedings consistent with these holdings. View "BOEING COMPANY v. US " on Justia Law

by
The case involves a bid protest action initiated by Oak Grove Technologies, LLC against the United States Department of the Army's award of a contract to F3EA, Inc. The contract, known as SOF RAPTOR IV, was for procuring training services for special forces. Oak Grove, a competing bidder, alleged that the bidding process was flawed and that F3EA had an unfair advantage due to an organizational conflict of interest involving the chairperson of the Source Selection Evaluation Board (SSEB), RM.The Court of Federal Claims reviewed the case and agreed with Oak Grove, finding that the Army's evaluation process was flawed. The court enjoined the Army from proceeding with the contract award to F3EA and ordered the Army to either restart the procurement process or reopen it to accept revised proposals. The court also sanctioned the government for failing to include material evidence in the administrative record, which delayed the proceedings and increased costs for Oak Grove.The United States Court of Appeals for the Federal Circuit reviewed the case and vacated the judgment and injunction issued by the Court of Federal Claims. The appellate court held that Oak Grove had waived its argument that the Army was required to hold discussions with bidders, that F3EA was not required to include teaming agreements in its proposal, and that the Army's investigation into RM's alleged misconduct was adequate. The court also found that the Court of Federal Claims erred in determining that Lukos, another bidder, was financially irresponsible and ineligible for the contract. However, the appellate court affirmed the sanctions imposed on the government for failing to compile a complete administrative record. The case was remanded for further proceedings consistent with the appellate court's opinion. View "OAK GROVE TECHNOLOGIES, LLC v. US " on Justia Law

by
In a procurement dispute, the Honolulu Board of Water Supply (BWS) solicited bids for a well-drilling project and disqualified Alpha, Inc. for not having the required contractor’s license. Alpha challenged the decision administratively and judicially, arguing that its bid was responsive and that the winning bidder, Beylik/Energetic A JV, was nonresponsive. BWS maintained that the administrative hearings officer and courts lacked jurisdiction to hear the protest because Alpha did not meet the statutory requirement that the protest concern a matter worth at least ten percent of the contract’s value.The Office of Administrative Hearings (OAH) concluded that the ten percent requirement was not jurisdictional and had jurisdiction to hear Alpha’s appeal. On the merits, OAH found that Alpha’s bid was nonresponsive due to the lack of a required subcontractor listing. The Circuit Court of the First Circuit affirmed OAH’s decision, agreeing that BWS could require a C-27 license for tree removal and that Alpha’s bid was nonresponsive. The Intermediate Court of Appeals (ICA) also affirmed, holding that the ten percent requirement related to standing, not jurisdiction, and that Alpha had standing to appeal.The Supreme Court of the State of Hawai‘i reversed the ICA’s decision, holding that the ten percent requirement is jurisdictional. The court concluded that Alpha did not meet this requirement, and therefore, OAH and the courts lacked jurisdiction to review BWS’s decision. The court also provided guidance on the merits, affirming BWS’s disqualification of Alpha’s bid for not listing a required subcontractor and not having the proper license for tree removal. View "Alpha Inc. v. Board of Water Supply" on Justia Law

by
Covenant Construction Services, LLC was the prime contractor on a federal construction project for a U.S. Department of Veterans Affairs facility in Iowa City, Iowa. Covenant subcontracted with Calacci Construction Company, Inc. to supply carpentry labor and materials. Calacci had a collective bargaining agreement (CBA) with two regional unions, requiring it to pay fringe-benefit contributions to the Five Rivers Carpenters Health and Welfare Fund and Education Trust Fund (the Funds). Despite multiple demands, Calacci failed to remit the required contributions.The Funds filed a lawsuit under the Miller Act to collect the unpaid contributions, liquidated damages, interest, costs, and attorneys' fees from Covenant and its surety, North American Specialty Insurance Company. The United States District Court for the Southern District of Iowa granted summary judgment in favor of the Funds, concluding that the Funds had standing to sue and that the Miller Act notice was properly served and timely.The United States Court of Appeals for the Eighth Circuit reviewed the case de novo. The court affirmed the district court's decision, holding that the Funds sufficiently complied with the Miller Act's notice requirements by sending the notice to Covenant's attorney, who confirmed receipt. The court also held that the notice was timely as it was filed within 90 days of the last day of labor on the project. Additionally, the court upheld the award of liquidated damages and attorneys' fees, finding that the CBA obligated Calacci to pay these amounts and that Covenant, as the prime contractor, was liable for the amounts due under the payment bond.The Eighth Circuit concluded that the Funds were entitled to recover the unpaid contributions, liquidated damages, and attorneys' fees from Covenant and its surety, affirming the district court's judgment. View "Five Rivers Carpenters v. Covenant Construction Services" on Justia Law

by
A sub-subcontractor, Diamond Services Corporation, entered into a contract with Harbor Dredging, a subcontractor, to perform dredging work in the Houston Ship Channel. The prime contract for the project was awarded to RLB Contracting by the U.S. Army Corps of Engineers, and RLB obtained a surety bond from Travelers Casualty and Surety Company of America. During the project, unexpected site conditions, including the presence of tires, caused delays and increased costs. Diamond continued working based on an alleged agreement that it would be compensated through a measured-mile calculation in a request for equitable adjustment (REA) submitted by RLB to the Corps. However, RLB later settled the REA for $6,000,000 without directly involving Diamond in the negotiations and issued a joint check to Harbor and Diamond for $950,000.The United States District Court for the Southern District of Texas dismissed some of Diamond's claims, including those for unjust enrichment and express contractual claims against RLB, but allowed Diamond's quantum meruit claim to proceed. The court also denied Travelers' motion to dismiss Diamond's Miller Act claims but required Diamond to amend its complaint to include proper Miller Act notice, which Diamond failed to do timely. Subsequently, the district court granted summary judgment in favor of RLB and Harbor, dismissing Diamond's remaining claims and striking Diamond's untimely second amended complaint.The United States Court of Appeals for the Fifth Circuit reviewed the case. The court affirmed the district court's summary judgment against Diamond's quantum meruit claims, holding that the express sub-subcontract covered the damages Diamond sought and that Diamond failed to provide evidence of the reasonable value of the work performed. The court also affirmed the dismissal of Diamond's Miller Act claim, as the damages sought were not recoverable under the Act. The court dismissed Diamond's appeal regarding the tug-expenses claim due to untimeliness. View "Diamond Services v. RLB Contracting" on Justia Law

by
3M Company operates a manufacturing facility in Cordova, Illinois, producing chemical products containing PFAS. The State of Illinois sued 3M, alleging that PFAS from the Cordova Facility contaminated the Mississippi River, violating state environmental laws. The State's complaint specifically excluded PFAS contamination from any other source, including AFFF used by the U.S. military at the nearby Rock Island Arsenal.The case was initially filed in Illinois state court. 3M removed it to the United States District Court for the Central District of Illinois, citing the federal officer removal statute, arguing that some contamination might have come from AFFF provided to the military, thus invoking a federal government contractor defense. The State moved to remand the case back to state court. The district court granted the motion, finding that the State's complaint excluded AFFF-related contamination, focusing solely on PFAS from the Cordova Facility.The United States Court of Appeals for the Seventh Circuit reviewed the case de novo. The court held that 3M could not satisfy the fourth element required for removal under the federal officer removal statute, which necessitates a colorable federal defense. The court noted that the State had unequivocally conceded that it would not seek relief for mixed PFAS contamination and that any recovery would be barred if contamination was not solely from the Cordova Facility. Consequently, 3M's government contractor defense was deemed irrelevant under the State's theory of recovery. The Seventh Circuit affirmed the district court's decision to remand the case to state court. View "Raoul v. 3M Company" on Justia Law

by
The case involves a qui tam action under the False Claims Act (FCA) brought by Relators against Great American Insurance Company (GAIC) and Native American Services Corporation (NASCO). The Relators allege that GAIC and NASCO fraudulently took control of DWG & Associates, Inc. (DWG), a company that had graduated from the Small Business Administration's (SBA) 8(a) program but was still performing on 8(a) contracts. The 8(a) program is designed to help small, disadvantaged businesses compete for federal contracts. DWG, initially owned and controlled by a disadvantaged individual, Gose, lost its eligibility when GAIC and NASCO allegedly took over its ownership and control without notifying the SBA or seeking a waiver, as required by the program's regulations.The United States District Court for the Middle District of Florida dismissed the Relators' claims with prejudice. The court found that DWG, having graduated from the 8(a) program, was no longer a "participant" and thus not subject to the program's ownership and control requirements. Consequently, the court ruled that Relators failed to allege any false claims. Additionally, the court held that fraudulent inducement related to bidding on government contracts was not actionable under the FCA and that Relators failed to meet the particularity requirements of Rule 9(b) for pleading fraud.The United States Court of Appeals for the Eleventh Circuit reversed the District Court's decision. The appellate court held that a business that has graduated from the 8(a) program but is still performing on 8(a) contracts remains a "participant" and is subject to the program's ownership and control requirements. The court further held that submitting bids and claims for payment under these circumstances without notifying the SBA or obtaining a waiver could constitute an actionable claim under the FCA. The court also found that Relators' complaint met the particularity requirements of Rule 9(b) by providing sufficient details about the alleged fraudulent conduct, including the specific contracts, task orders, and the date DWG became ineligible to bid. The case was remanded for further proceedings consistent with the appellate court's opinion. View "Berry v. Native American Services Corporation" on Justia Law

by
Yorktown Systems Group Inc. and Threat Tec LLC, both defense contractors, entered into a mentor-protégé relationship under the Small Business Administration’s program to jointly pursue government contracts. They formed a joint venture (JV) and were awarded a $165 million contract with the U.S. Army. The JV agreement allocated specific work shares to each company. However, the relationship soured, and Threat Tec attempted to terminate Yorktown’s subcontract, effectively cutting Yorktown out of its share of the contract.The United States District Court for the Northern District of Alabama granted Yorktown a preliminary injunction, preventing Threat Tec from terminating the subcontract and depriving Yorktown of its rights under the JV agreement. The court found that Yorktown had shown a substantial likelihood of success on its breach of contract and breach of fiduciary duty claims and faced irreparable harm. The court noted that Threat Tec’s CEO had made false statements and lacked candor, leading to the belief that Threat Tec’s motives were unethical.The United States Court of Appeals for the Eleventh Circuit reviewed the case and affirmed the district court’s decision. The appellate court found no clear error in the district court’s factfindings and concluded that the district court acted within its discretion. The court held that Threat Tec, as the managing member of the JV, owed fiduciary duties of loyalty and care to Yorktown and likely breached those duties by attempting to cut Yorktown out of its contractually specified workshare. The court also agreed that Yorktown faced irreparable harm, including potential damage to its business reputation and the loss of highly skilled employees, which could not be remedied by monetary damages alone. View "Yorktown Systems Group Inc. v. Threat TEC LLC" on Justia Law