Alcoa Power Generating Inc. v. FERC

by
The Alcoa Power Generating Company ("Alcoa") petitioned for review of two orders of the Federal Energy Regulatory Commission ("Commission") with respect to the relicensing of its Yadkin Project facilities in North Carolina. At issue was whether the petition for review was ripe in light of on-going state administrative review and stay of certification and whether the certifying agency waived its authority by not issuing a certification that was effective and complete within one year under section 401 of the Clean Water Act ("Act"), 33 U.S.C. 1341(a)(1). The court held that the petition was ripe for review where the waiver issue was fit for review and the legally cognizable hardship that Alcoa would suffer from delay sufficed to outweigh the slight judicial interest in the unlikely possibility that the court may never need to decide the waiver issue. The court also held that there was no waiver issue where the "effective" clause would not operate to delay or block the federal licensing proceeding beyond section 401's one-year period.