Justia Government Contracts Opinion Summaries

Articles Posted in Construction Law
by
The Supreme Court reversed the decision of the district court granting summary judgment in favor of Plaintiffs in this action seeking to recover delinquent contributions to various trust funds for construction on a state construction project, holding that the right of action under a payment bond statute extends to any amount due an employee, meaning any amount that is traceable specifically to an employee.One of the subcontractors hired to work on the project failed to make contributions to various trust funds for its employees' work on the project, as required by trust agreements and a collective bargaining agreement. The trusts (Plaintiffs) sought to recover the delinquent contributions from the public payment bond associated with the project by suing Defendant, the surety for the payment bond. The district court granted summary judgment for Plaintiffs. On appeal, the parties disputed whether Utah Code 63G-6-505(4) limits the right of action on a payment bond to amounts due to an employee or encompasses claims for any amounts due for an employee or on the employee's behalf. The Supreme Court reversed, holding that the right of action under the public payment bond statute contemplates recovery of any specific benefit that is due a person in the sense of being traceable to that person. View "McDonald v. Fidelity & Deposit Co. of Maryland" on Justia Law

by
After Phelps was awarded a public works contract by the CDCR, another bidder successfully challenged the award, obtaining a ruling in a San Diego trial court that Phelps's bid was "non-responsive as a matter of law" due to its inclusion of "non-waivable mathematical/typographical errors." Phelps then filed suit against CDCR, seeking to recover the costs it expended on the project. The trial court held that the San Diego trial court's ruling was itself the result of a defect in the competitive bidding process caused solely by CDCR, and entered judgment in favor of Phelps.The Court of Appeal reversed, holding that judgment on the pleadings should have been granted. The court held that the language in Public Contract Code section 5110 provides that the parties to a challenged public contract may enter into that contract pending final resolution of the challenge, but if the challenge is resolved by invalidation because the public entity was at fault, the contractor may recover. Applying section 5110 in this case, the court held that the contract was invalidated for a material error in Phelps's bid, not for any defect in the competitive bidding process, much less a defect caused solely by CDCR. Therefore, section 5110 could not provide a basis for recovery. The court held that application of the doctrine of collateral estoppel would produce the same result, and rejected Phelps's late-raised alternative ground. However, the court affirmed the trial court's denial of recovery on CDCR's cross-complaint for disgorgement. View "Hensel Phelps Construction Co. v. Department of Corrections and Rehabilitation" on Justia Law

by
After Mount Diablo School District hired Taber to modernize eight school campuses, the plaintiffs challenged the District’s use of a lease-leaseback agreement for the construction project. The court of appeal affirmed the dismissal of most of plaintiff’s claims, except a claim against Taber of conflict of interest. Plaintiff alleged Taber provided preconstruction services regarding the project, so a conflict of interest arose when the District subsequently awarded Taber the contract. The court of appeal affirmed summary judgment in Taber’s favor, finding no violation of Government Code section 1090(a). Section 1090 only prohibits a contract made by a financially-interested party when that party makes the contract in an “official capacity.” Where the financially-interested party is an independent contractor, section 1090 applies only if the independent contractor can be said to have been entrusted with “transact[ing] on behalf of the Government.” In this case, it cannot reasonably be said that Taber was hired to engage in or advise on public contracting on behalf of the District. The District contracted with Taber for Taber to provide preconstruction services in anticipation of Taber completing the project. Taber provided those services (planning and setting specifications) in its capacity as the intended provider of services, not as a de facto official of the District. View "California Taxpayers Action Network v. Taber Construction, Inc." on Justia Law

by
Fistes appealed from the trial court's judgment sustaining without leave to amend defendants' demurrer to Fistes' third amended complaint, seeking a declaration that the contract the District awarded to GDL for the remediation of school properties was void due to violations of the Public Contract Code and the Government Code.The Court of Appeal held that Fistes alleged facts sufficient to establish standing under Code of Civil Procedure section 526a based on its payment of state taxes that fund the District. The court also held that the district court erred in sustaining the demurrer based on uncertainty without leave to amend. In this case, although Fistes has not adequately alleged a cause of action against the Lopezes, it has made a sufficient showing for leave to amend. Accordingly, the court reversed and remanded for further proceedings. View "A.J. Fistes Corp. v. GDL Best Contractors, Inc." on Justia Law

by
The Subletting and Subcontracting Fair Practices Act governs public works projects, requires a prime contractor to obtain the awarding authority's consent before replacing a subcontractor listed in the original bid (Pub. Contract Code 4107(a)), and limits the awarding authority’s ability to consent. If the original subcontractor objects to being replaced, the awarding authority must hold a hearing. San Francisco entered a contract with prime contractor Ghilotti for a major renovation of Haight Street. Consistent with its accepted bid, Ghilotti entered a contract with subcontractor Synergy for excavation and utilities work. After Synergy broke five gas lines and engaged in other unsafe behavior, the city invoked a provision of its contract with Ghilotti to direct Ghilotti to remove Synergy and substitute a new subcontractor. Under protest, Ghilotti terminated Synergy and identified two potential replacement contractors. Synergy objected. A hearing officer determined that Synergy’s poor performance established a statutory ground for substitution. Synergy and Ghilotti argued that the hearing officer lacked jurisdiction because Ghilotti had not made a “request” for substitution. The trial court agreed. The court of appeal reversed. Although the statute contemplates that the prime contractor will normally be the party to seek substitution, the procedure followed here “complied in substance with every reasonable objective of the statute.” View "Synergy Project Management, Inc. v. City and County of San Francisco" on Justia Law

by
In 2007, the VA sought to lease space for a Parma, Ohio VA clinic. A pre-solicitation memorandum stated that the building must comply with the Interagency Security Committee (ISC) Security Design Criteria. The subsequent Solicitation discussed the physical security requirements. Premier submitted a proposed design narrative that did not address those requirements. In 2008, Premier and the VA entered into a Lease. Premier was to provide a built-out space as described in the Solicitation. About 18 months later, the VA inquired about Premier’s first design submittal, advising Premier to obtain access to the ISC standards, because “the project needs to be designed according to the ISC.” The ISC denied Premier’s request, stating that the documents had to be requested by a federal contracting officer who has a “need to know.” The VA forwarded copies of three ISC documents. Some confusion ensued as to which standard applied. The VA then instructed Premier to disregard the ISC requirements and to incorporate the requirements from the latest VA Physical Security Guide. Months later, the VA changed position, stating that “[t]he ISC is the design standard.” Premier’s understanding was that only individual spaces listed in a Physical Security Table needed to comply with the ISC. The VA responded that the entire building must conform to the ISC at no additional cost. Premier constructed the building in accordance with the ISC standards then unsuccessfully requested $964,356.40 for additional costs. The Federal Circuit affirmed summary judgment in favor of the government. The contract unambiguously requires a facility conforming to ISC security requirements. View "Premier Office Complex of Parma, LLC v. United States" on Justia Law

by
The Second Circuit affirmed the district court's summary judgment dismissal of all claims in the Second Amended Complaint against defendants in an action stemming from construction projects with the U.S. Army Corps of Engineers. The court held that MES's claims failed to articulate any support for its accusations that Safeco breached its contractual obligations or engaged in bad faith or tortious conduct. The court noted that the claim that Safeco acted inappropriately by attending the cure meetings was particularly frivolous. In this case, MES failed to identify any good faith basis, in law or on the basis of the agreements at issue, for its assertion that Safeco had no right to take steps to meet its obligations under the surety bonds. The court sua sponte awarded Safeco double costs. View "M.E.S., Inc. v. Safeco Insurance Co. of America" on Justia Law

by
The Vermont Agency of Transportation (VTrans) appealed the Transportation Board’s order granting judgment to W.M. Schultz Construction, Inc. in this contract dispute. Schultz entered into a contract with VTrans in December 2013 to replace four bridges destroyed by Tropical Storm Irene. Three bridges were completed without incident. This dispute centered on the fourth bridge, referred to as “Bridge #19.” The Bridge #19 project involved the construction of a single-span steel-girder bridge over the White River in Rochester, Vermont. The west abutment was to be placed on a deep pile foundation and the east abutment (Abutment #2) was to be placed on ledge. The work was to begin in April 2014 and be completed in a single construction season. The Board concluded that Schultz encountered “differing site conditions” in carrying out its bridge-construction project and that it was entitled to an equitable adjustment for costs it incurred as a result. VTrans appealed, arguing the Board misread the contract materials and otherwise erred in granting judgment to Schultz. Finding no reversible error, the Vermont Supreme Court affirmed. View "W.M. Schultz Construction, Inc. v. Vermont Agency of Transportation" on Justia Law

by
The City of Olympia, Washington contracted with NOVA Contracting, Inc. to replace a deteriorating culvert. The contract contained a "notice of protest" provision, which was taken from the Washington Department of Transportation's "standard Specifications for Road, Bridge, and Municipal Construction (2012) manual. NOVA sued the City for breach of the implied covenant of good faith and fair dealing; the City moved to dismiss based in part on NOVA's filature to file a protest first before taking the City to court. The trial court dismissed NOVA's claim, but the Court of Appeals reversed. The Washington Supreme Court has addressed this written notice issue twice before; the Court of Appeals interpreted those holdings, however, as only applying to claims for cost of work performed and not claims for expectancy and consequential damages. The Supreme Court held the two prior cases applied even to claims of expectancy and consequential damages. Therefore, the Court reversed the appellate court and remanded this case for further proceedings. View "NOVA Contracting, Inc. v. City of Olympia" on Justia Law

by
In holding that the successor judge in this case had authority to dismiss Plaintiff’s claims for breach of contract and consequential damages and committed no reversible error by doing so, the Supreme Court repudiated any language in its precedent that suggests that a successor judge on a case is bound by nonfinal decisions and rulings made by his predecessor.Plaintiff, who was hired by the Utah Department of Transportation (UDOT) to work on different construction projects, filed various claims against UDOT and other contractors on the projects. UDOT moved for summary judgment on claims for breach of contract on the “Arcadia” project and claims seeking consequential damages. Judge Kennedy, the original judge assigned to the case, denied both motions. Judge Kennedy was then replaced in this case by Judge Harris. Judge Harris ultimately dismissed Plaintiff’s claims for breach of contract and consequential damages. Plaintiff filed this interlocutory appeal, arguing that Judge Harris violated the so-called coordinate judge rule, which Plaintiff alleged limits the discretion of a successor judge to revisit decisions of a predecessor. The Supreme Court disagreed, holding (1) a successor judge has the same power to review nonfatal decisions that a predecessor would have had; and (2) Judge Harris did not commit reversible error by dismissing the claims at issue. View "Build v. Utah Department of Transportation" on Justia Law