After Rio School District’s new school was completed, the District and its general contractor (FTR) engaged in a decade-long legal battle, resulting in a judgment for FTR exceeding $9 million. Public Contract Code section 7107 allows a public entity to withhold funds due a contractor when there are liens on the property or a good faith dispute concerning whether the work was properly performed. The trial court assessed penalties against District because it did not timely release the retained funds. The court of appeal affirmed in part. A dispute over the contract price does not entitle a public entity to withhold funds due a contractor; the doctrine of unclean hands does not apply to section 7107; the trial court properly rejected the District's action under the False Claims Act, Government Code section 12650 and properly assessed prejudgment interest, subject to adjustment for any extra work claims found untimely on remand. The trial court erred in its interpretation of a contract provision imposing time limitations to submit the contractor's claims for extra work as requiring a showing of prejudice and erred in awarding fees for work not solely related to FTR's section 7107 cause of action. View "East West Bank v. Rio School Dist." on Justia Law

by
The Department of Agriculture’s Rural Utilities Service (RUS) made a $267 million loan to Open Range to finance construction of wireless broadband networks in 540 RUS-approved markets. Open Range subcontracted with G4S. The FCC suspended a permit, so that Open Range lost the spectrum rights necessary to operate the planned network. RUS gave notice of its intent to terminate remaining funds on the loan unless Open Range could obtain replacement rights. Open Range began failing to meet its obligations to subcontractors. The Secretary of Agriculture made loan money available, provided a press release, and offered to reassure subcontractors, but Open Range was unable to regain the full spectrum rights necessary to complete the original project. RUS and Open Range executed an amendment to reflect a loan amount reduced to $180 million, and 160 RUS-approved markets, but Open Range remained unable to satisfy its debts and filed for bankruptcy. G4S filed suit. The Claims Court held that G4S was not a third party beneficiary to the agreement. The Federal Circuit affirmed, stating that G4S asked that the government incur liability simply because it talked to the individuals in charge of a failing project in an attempt to fix the problems. View "G4S Tech., LLC v. United States" on Justia Law

by
In 2003, the VA entered into a contract with Reliable for electrical improvements at a VA medical center, requiring installation of three backup generators, “new and of the most suitable grade.” Federal Acquisition Regulation 52.211-5, incorporated by reference, requires that supplies be “new, reconditioned, or remanufactured,” and defines “new” as “composed of previously unused components.” Reliable sub-contracted to Fisk, which contracted with DTE. In 2004, DTE delivered two Cummins Power Generation generators to the construction site. The VA’s senior resident engineer inspected the generators and determined that they were not “new.” He wrote to Reliable, stating: They show a lot of wear and tear including field burns to enlarge mounting holes. Are they new and will you certify them as such? I cannot pay you … without that certification. Fisk and Reliable initially agreed that the generators did not meet the contract specification. After investigation, they concluded that the generators, manufactured in 2000, had been previously purchased by others but never used. Fisk obtained different generators, which were accepted by the VA. In 2007, Reliable submitted a claim, seeking $1,100,000 for additional costs incurred as a result of rejection of the original generators. In 2013, the Board of Contract Appeals denied Reliable’s claim. The Federal Circuit vacated, holding that the Board erred in its interpretation of the contract. View "Reliable Contracting Grp., LLC v. Dep't of Veterans Affairs" on Justia Law

by
Lydig Construction was the general contractor on a large public works project. Martinez Steel was the original steel supply subcontractor on the project. Lydig sued Martinez for additional costs Lydig incurred because Martinez failed to timely supply steel for the project; Lydig, with the public agency's approval, had been required to replace Martinez as the steel supplier. Lydig moved for a right to attach order and a writ of attachment and presented the trial court with its business records and declarations from its employees. Martinez opposed Lydig's motion and presented declarations from one of its employees that set forth its contention Lydig owed it for, among other items, steel Martinez had delivered to the project. Martinez filed a cross-complaint in which it alleged claims that, if successful, would entirely offset Lydig's claims against it. The trial court granted Lydig's motion and issued writs of attachment in the amount of $203,315. The court of appeal affirmed, rejecting Martinez's contentions that its cross-complaint, as a matter of law, prevented the trial court from issuing a writ of attachment against it and that Lydig's application for a writ of attachment was not supported by substantial evidence. View "Lydig Constr., Inc. v. Martinez Steel Corp." on Justia Law

by
In 2004, K-Con entered into a contract with the federal government to construct a Coast Guard building in Port Huron Michigan for $582,641. Once K-Con finished, the government imposed liquidated damages of $109,554 for tardiness of 186 days in completion. KCon sued, seeking remission of the liquidated damages on two grounds—that the contract’s liquidated-damages clause was unenforceable and that KCon was entitled to an extension of the completion date. KCon also requested additional compensation based on work performed in response to government requests that K-Con alleges amounted to contract changes. The Court of Federal Claims held that the contract’s liquidated damages clause was enforceable; that K-Con did not comply with the written-notice precondition for invoking the contract clause governing changes; and that K-Con’s claim for an extension on the completion date must be dismissed for lack of jurisdiction. The Federal Circuit affirmed. K-Con failed to comply with the changes clause, and its after-the-fact speculations about what would have happened had it complied do not create a genuine dispute of material fact regarding whether it should be excused for its failure. View "K-Con Bldg. Sys., Inc. v. United States" on Justia Law

by
FTR has constructed buildings for public entities for 15 years. In 1999, FTR submitted the winning bid of $7.345 million to construct a District school. During construction, FTR submitted approximately 150 proposed change orders (PCO). FTR claimed some were necessary because the District’s plans were inadequate or misleading. The District denied most of the PCOs on the grounds that the work was covered under the basic contract, the amounts claimed were excessive, or that a PCO was not timely under the contract. Construction was completed in 2001. Public Contract Code 7107 allows a public entity to withhold funds due a contractor when there are liens on the property or a good faith dispute concerning whether the work was properly performed. The court of appeal held that the trial court properly assessed penalties against District because it did not timely release retained funds; properly rejected the District's action under the False Claims Act, Government Code 12650; and properly assessed prejudgment interest. The court erred in its interpretation of a contract provision imposing time limitations to submit claims for extra work as requiring a showing of prejudice and erred in awarding fees for work not solely related to FTR's section 7107 cause of action. View "FTR Int'l, Inc. v. Rio Sch. Dist." on Justia Law

by
The School District entered into a construction contract with Amoroso. Pursuant to Public Contract Code 22300, Amoroso elected to have the retention held in an escrow account in the form of securities. The escrow agreement stated that “District shall have the right to draw upon the securities and/or withdraw amounts from the Escrow Account in event of default by Contractor as determined solely by District.” The District gave written notice of material breach on March 30, 2011, based on Amoroso’s failure to complete, timely or at all, any of the three project phases and requested that Amoroso cure by April 4. Amoroso contested the assertions of material breach by letter dated April 1. The District sent notice of termination on April 18 and filed suit. On April 28, the parties entered into an “Exit and Demobilization Agreement,” “in lieu of any final termination or statement of default under the Contract.” The District sent a letter requesting withdrawal of $3.5 million from the escrow account, attaching its attorney’s memorandum as to why withdrawal was permissible. Amoroso unsuccessfully sought an injunction. The court of appeal affirmed, rejecting Amoroso’s claim that a public project owner must await judicial resolution of the underlying contract dispute before it can withdraw retention funds. View "Pittsburg Unified Sch. Dist. v. S.J. Amoroso Constr. Co., Inc." on Justia Law

by
The Jackson County Board of Education petitioned for a writ of mandamus to direct the Circuit Court to enter an order dismissing the complaint of D.C. Pruett Contracting Company, Inc. on the ground of sovereign immunity. Pruett Contracting submitted a proposal for renovations to the Pisgah High School gymnasium. The Jackson County superintendent of education executed a purchase order authorizing Pruett Contracting to make certain renovations to the gymnasium, totaling $231,309. Pruett Contracting then began renovating the gymnasium. The Superintendent later received a letter from the State of Alabama Building Commission stating that "all work on the renovation of the Pisgah High School gymnasium [was] to stop immediately" because the project had not been submitted to or approved by the Building Commission. The Board instructed Pruett Contracting to cease all work on the gymnasium. Pruett Contracting submitted an invoice to the Board for the work that had been performed prior to the letter. Months later, because it had not received payment for its work, Pruett Contracting sued the Board, alleging breach of contract and unjust enrichment and seeking recovery of damages on theories of quantum meruit, work and labor done, open account, and account stated. The Board moved the court to dismiss the complaint, arguing that it was entitled to sovereign immunity as to the claims alleged by Pruett Contracting and that the court therefore lacked subject-matter jurisdiction over the action. Pruett Contracting responded, arguing that this case involved a protected property interest, that immunity was thus precluded, and that the court had subject-matter jurisdiction over the action. The Supreme Court concluded the Board established that it was entitled to sovereign immunity and that the trial court did not have subject-matter jurisdiction over this action; therefore, the action had to be dismissed. Because the Board demonstrated a clear legal right to an order directing the Circuit Court to dismiss Pruett Contracting's complaint, the Supreme Court granted the Board's petition for a writ of mandamus and directed the Circuit Court to dismiss Pruett Contracting's complaint. View "D.C. Pruett Contracting Company, Inc. v. Jackson County Board of Education" on Justia Law

by
The Georgia Department of Corrections (GDOC) entered into a construction contract with Lewis Walker Roofing (Walker Roofing) to re-roof several buildings at Valdosta State Prison. The Contract contained two “no assignment” clauses, and as a prerequisite to contracting with GDOC, Walker Roofing was required to obtain payment and performance bonds. It obtained such payment and performance bonds from Developers Surety and Indemnity Company. Walker Roofing did not complete its work within the time frame required by the Contract, and GDOC declared Walker Roofing in default. Developers Surety did not notify GDOC within 25 days of receipt of GDOC's notice of default regarding whether it would remedy the default or perform the contract. However, approximately three months after the declaration of default, Developers Surety gave GDOC the option of entering into a contract with another company for the completion of the work. GDOC then contracted with that company to finish the project. Under the payment and performance bonds and prior to Walker Roofing's default, Developers Surety had provided financial assistance to Walker Roofing. Developers Surety filed suit against GDOC for breach of contract and for a declaratory judgment that it had no obligation under the payment and performance bond it issued to Walker Roofing on behalf of GDOC. GDOC filed a counterclaim for breach of contract. The parties filed cross-motions for summary judgment, and the trial court determined that Developers Surety's claims were not barred by sovereign immunity and that GDOC had breached the construction contract as a matter of law. It concluded that GDOC waived its sovereign immunity by entering into the contract with Walker Roofing, and that the doctrine of equitable subrogation gave Developers Surety the ability to file suit against GDOC once it incurred liability and paid the obligations of its principal under the bond. Consequently, the trial court granted summary judgment to Developers Surety and denied it to GDOC; in the same order, the trial court entered judgment in favor of Developers Surety in the amount equal to the "financial assistance" Developers Surety provided to Walker Roofing. The Supreme Court granted certiorari to the Court of Appeals to consider whether the State’s sovereign immunity was waived for the claim Developers Surety made on its contract with the State. The Supreme Court found that immunity was indeed waived in this instance, and accordingly, it affirmed the judgment of the Court of Appeals. View "Georgia Dept. of Corrections v. Developers Surety & Indemnity Co." on Justia Law

by
A contractor entered into a public works contract to modernize a building at a Santa Clara County community college. Will was the subcontractor for the heating, ventilation, and air conditioning (HVAC) work. The subcontract provided that the project was to be built according to the specifications of the prime contract. The subcontract and general contract did not specify whether Will was required to fabricate any material necessary to complete the HVAC work. The subcontract required Will to “pay not less than the [applicable prevailing wage] to all laborers, workmen, and mechanics employed by him at the project site.” California’s prevailing wage law generally requires that workers employed on public works be paid the local prevailing wage for work of a similar character. (Lab. Code,1771.) Since 1991, Will has fabricated materials at a permanent, offsite facility it operates in Hayward. An employee of Will complained to the Department of Industrial Relations, Division of Labor Standards Enforcement alleging he should have been paid prevailing wages for work related to the project, involving the fabrication of sheet metal at the Hayward facility. DLSE issued a civil wage and penalty assessment. The Department of Industrial Relations reversed, in favor of Will. The trial court reversed. The court of appeal held that offsite fabrication is not covered by the prevailing wage law if it takes place at a permanent, offsite manufacturing facility and the location and existence of that facility is determined wholly without regard to the particular public works project. View "Sheet Metal Workers’ Int'l. Ass'n v. Duncan" on Justia Law