The respondents, two developers and an architectural firm, Stevens & Wilkinson of South Carolina, Inc. (S&W), entered into a Memorandum of Understanding (MOU) with the City of Columbia as part of a larger project team to develop a publicly-funded hotel for the Columbia Metropolitan Convention Center. The City eventually abandoned its plan under the MOU, and the respondents brought suit on several causes of action including breach of contract and equitable relief. The City moved for summary judgment arguing the MOU was not a contract and therefore the contract claims failed. The circuit court agreed and, rejecting the equitable claims as well, granted summary judgment in favor of the City. The respondents appealed and the court of appeals affirmed in part and reversed in part. The Supreme Court reversed. Because the MOU was comprised of agreements to execute further agreements, there was no meeting of the minds on numerous material terms which had not yet been defined. Accordingly, the court of appeals was reversed with respect to that portion of the court's judgment; the Supreme Court held the MOU was unenforceable as a matter of law. The Supreme Court agreed with the circuit court and reinstated its judgment in favor of the City. View "Stevens & Wilkinson of South Carolina, Inc. v. City of Columbia" on Justia Law

by
In April 2003, the City of Columbia entered into a Memorandum of Understanding (MOU) with Stevens & Wilkinson of South Carolina, Inc. (S&W) and several other parties, to develop a publicly-funded hotel adjacent to the Columbia Metropolitan Convention Center. As architect, S&W was to complete sufficient preliminary design work to determine a guaranteed maximum price for the project, which would be used by the City to obtain municipal bond funding to cover the cost of the hotel. Pursuant to the MOU, the construction company was to pay S&W directly. On June 26, 2003, the City received a letter stating S&W would complete its preliminary design on July 10, 2003, and would then stop working until the bond financing for the hotel was finalized. Realizing this could delay the start of construction, S&W offered to continue working the remaining ninety days until the anticipated bond closing date of October 13, 2003, but required assurance it would be compensated for the work it performed during this time frame. It provided an estimate requiring $650,000 and $75,000 per week after that. On July 30, the City approved "$650,000 for interim architectural design services for a period of 90 days prior to bond closing." The bond closing did not occur as scheduled, but S&W nevertheless continued to work. S&W submitted an invoice to the City for $697,084.79 for work that took place from July 10 to December 15, 2003. By letter dated December 17, 2003, S&W informed the construction company that the City had voted that day "to advance [$705,000.000] to the design team for design services and expenses. Because under the MOU the construction company was to pay S&W, not the City, the construction company agreed to reimburse the City for the funds paid to S&W after the bond closing. The City paid S&W's invoice. S&W continued to work on the project, but in March 2004, the City abandoned its plans under the MOU and ended its relationship with S&W. S&W received no further compensation and sued the City for breach of contract under the MOU and the July 2003 agreement. The City argued there was no separate agreement and the payment of interim fees was merely an advance on fees under the MOU and furthermore, the MOU provided that S&W was to be paid by the construction company, not the City. The trial court granted partial summary judgment in favor of S&W, finding a contract existed between it and the City. On certiorari, the City conceded a contract exists, but argued the contract terms have been satisfied. The Supreme Court found the City's arguments were unpreserved and affirmed as modified. View "Stevens & Wilkinson of South Carolina, Inc. v. City of Columbia" on Justia Law

by
The Eastern Municipal Water District (EMWD) hired general contractor S.J. and Burkhardt, Inc. (SJB) for a public works construction project in 2006. Safeco Insurance Company (Safeco) executed performance and payment bonds for the project. Plaintiff Golden State Boring & Pipe Jacking, Inc. (GSB) was a subcontractor for the project, completing its work by September 2006, but it did not receive payment. In March 2008, SJB sent a voluntary default letter to Safeco. In July 2008, GSB sued SJB, EMWD, and Safeco for the unpaid amounts under the contract, separately seeking payment from Safeco under its payment bond. EMWD filed a cross-complaint to interplead retained sums. Safeco made a motion for summary judgment on the cause of action for payment under the bond on the ground that GSB’s claim was untimely. The trial court granted the motion, finding that there had been three cessations of labor that triggered GSB’s duty to file a stop notice in order to secure payment under Safeco's payment bond. At a subsequent court trial on the contract claims, GSB was awarded judgment against SJB, and Safeco was awarded judgment on the interpleader action. GSB appealed the summary judgment ruling, arguing: (1) the trial court erroneously overruled its objections to evidentiary matters presented in support of Safeco’s summary judgment; and (2) the court erred in finding the action was untimely. Finding no reversible error, the Court of Appeal affirmed. View "Golden State v. Eastern Municipal Water Dist." on Justia Law

by
In 2006, the Federal Bureau of Prisons issued a Request for Proposals for the “design-build” construction of a federal correctional institution. The project involved a “cut-to-fill” site, meaning that the ground had to be leveled by excavating materials from one area of the site and using those materials to fill lower areas. Based on information in the solicitation documents and prior experience, BH believed the New Hampshire Department of Environmental Sciences would approve a permit for a one-step-cut-to-fill construction plan and calculated its bid price, $238,175,000, accordingly. The contract provided liquidated damages of $8,000 for each day completion was overdue. The NHDES rejected the application. BH advised the government of the implications of NHDES restrictions, but did not refuse to proceed or request that the government intervene with the NHDES. According to BH, the restrictions were contrary to generally accepted industry practice. Upon completion of cut-to-fill operations, BH submitted a Request for Equitable Adjustment, seeking $7,724,885 for excess costs. The Contracting Officer and the Claims Court rejected the request, finding that the Permits and Responsibilities clause placed the burden of obtaining and complying with state and local permits on BH “without additional expense to the Government;” that BH had not alleged violation of the implied duty of good faith; and that, because the government did not control the NHDES, there was no basis for imposing liability for constructive change. The Federal Circuit affirmed.View "Bell/Heery v. United States" on Justia Law

by
American General Contractors, Inc. ("AGC"), appealed a judgment assessing liability and awarding damages and interest for the cost of delays in the construction of the Williams County Law Enforcement Center in Williston. C&C Plumbing and Heating, LLP ("C&C"), the successful bidder for the mechanical prime contract, filed suit when construction the center was delayed approximately two years after "substantial completion" was supposed to have happened. The district court concluded it was appropriate for the County and AGC to share responsibility for providing temporary shelter and heat on the project. The court apportioned 47 percent of the liability for the costs of the delay for the three and one-half months of active interference to the County and 53 percent to AGC, for the four months delay inherent to the industry. The court awarded C&C approximately $73,000 on its claim against the County. After offsetting amounts owed between the parties, the court awarded AGC approximately $424,000 on its claim against the County. The court awarded Davis Masonry approximately $96,000 from AGC for masonry work completed under its subcontract with AGC, and rejected AGC's claimed offsets to that amount. Davis had provided heat, cover and shelter for the project during cold weather and sought $649,000 from the County and AGC for that expense including prompt payment interest. Davis had settled with the County for $530,000, and the court ruled AGC was responsible for 53 percent of the remaining $119,000, or $63,070. AGC argues the district court erred in determining AGC was liable for any of the costs incurred from the delay under its contract with the County. Finding no reversible error, the Supreme Court affirmed the district court. View "C&C Plumbing and Heating, LLP v. Williams County" on Justia Law

by
MMS Construction & Paving, L.L.C. entered into a subcontract with Head, Inc. to pave asphalt runway shoulders at Altus Air Force Base in Oklahoma. The project was delayed and MMS, expressing concern that Head had not been making agreed payments, quit the job. MMS also complained that completing the job would be more expensive than it originally believed because certain requirements were being imposed that Head said would be waived. After MMS quit, Head finished the job, relying on other subcontractors. MMS sued Head on state-law claims of breach of contract, tortious breach of contract, quantum meruit, and misrepresentation, and brought a claim under the federal Miller Act on Head’s surety bond for the project. Head filed a counterclaim, alleging that MMS breached the contract. After a jury trial, MMS was awarded damages and attorney fees. Head filed a motion for judgment as a matter of law or for a new trial, both of which the district court denied. Head appealed, arguing: (1) the evidence at trial was insufficient to show that Head breached the contract; (2) if there was a breach, it was not material; (3) an Oklahoma statute limited MMS’s breach-of-contract damages to the amount unpaid plus interest; (4) the evidence was not sufficient to establish MMS’s alleged lost-profits damages for breach of contract; (5) MMS did not present sufficient evidence to prove misrepresentation or any damages from misrepresentation, MMS waived the misrepresentation claim, and the award of misrepresentation damages duplicated the award of damages for breach of contract; and (6) MMS was not entitled to attorney fees from Head because the Miller Act does not allow recovery of those fees. Upon careful consideration of the district court record, the Tenth Circuit reversed damages award based on the misrepresentation claim because the jury’s award was not supported by any evidence at trial. On all other issues, the Court affirmed. View "MMS Construction & Paving v. Head, Inc., et al" on Justia Law

by
Northern, operated by VanDuinen, was a general contractor on public construction projects, legally required to obtain surety bonds. Hanover was Northern’s bonding agent and required Northern to enter into an Indemnity Agreement, which VanDuinen signed in his individual capacity and as Northern’s President. The Midway Airport Project was financed by the FAA and managed by Parsons. In 2008 Northern won the bid and began subcontracting. in 2009 subcontractors complained that Northern failed to pay them in accordance with the bonds and contracts. Work was halted, resulting in a separate complaint, by Parsons, for failure to complete the Project as required. The FAA opted to retain possession of remaining contract funds, $127,086.00, pending resolution of the disputes and completion of the work. Hanover received claims from subcontractors McDaniel ($127,452.78) and Rex Electric ($78,495.00) and a claim for performance from Parsons. Hanover demanded collateral under the Agreement. Northern refused to post collateral or to indemnify Hanover. In 2009 McDaniel filed for bankruptcy; the bankruptcy trustee sued Hanover seeking payment for work performed. In 2012, Hanover paid the trustee $127,452.78 to resolve both McDaniels’s and Rex Electric’s claims. Hanover resolved Parson’s claim by stepping in as general contractor and arranging for completion of the Project. Parsons paid Hanover the $127,086.00 of contract funds the FAA had withheld. Hanover sued Northern and VanDuinen. The district court granted summary judgment in Hanover’s favor. The Seventh Circuit affirmed. The Agreement is unambiguous. Northern breached it, and Hanover is entitled to contractual damages. View "Hanover Ins. Co. v. Northern Bldg. Co." on Justia Law

by
Project labor agreements (PLAs) are used in the construction industry to set common conditions of employment for large projects involving multiple subcontractors and unions. On a public construction project, a PLA can be entered into by the governmental unit paying for the project or by its general contractor; the other party is a labor organization. If the governmental unit enters into a PLA, all contractors bidding on the project must agree to abide by it. Opponents argue that PLAs discourage nonunion contractors from bidding on government contracts and increase construction costs. Proponents, such as the trades councils, claim that PLAs enhance job-site cooperation and reduce labor disputes. The federal government has gone back and forth on allowing PLAs. Michigan passed the first version of the Fair and Open Competition in Governmental Construction Act in 2011, restricting the use of PLAs on publicly funded projects. Following entry of an injunction, that version was superseded by an amended act, passed in 2012. The district court enjoined the current version as preempted by the National Labor Relations Act. The Sixth Circuit reversed, finding that the act furthers Michigan’s proprietary goal of improving efficiency in public construction projects, and is no broader than necessary to meet those goals. View "MI Bldg. & Constr. Trades Council v. Snyder" on Justia Law

by
Plaintiff Victor Virgin Construction Corporation appealed a Superior Court remitting a jury award following an advisory jury finding of breach of contract and negligent misrepresentation by defendant New Hampshire Department of Transportation (DOT). DOT cross-appealed, asking that the award be further reduced. In 2008, Virgin bid on a DOT project to replace a stone box culvert located underneath Depot Road in Hollis. Virgin submitted the lowest bid and was awarded the contract. After completion of the project, DOT paid Virgin the sum agreed to in the contract with only a minor upward adjustment. Virgin sued DOT for both breach of contract and negligent misrepresentation. The trial court denied DOT's request to bifurcate the trial; subsequently the jury found in favor of Virgin. DOT then moved for a new trial or to set aside the jury's damages award. The trial court granted remittitur, but did no enter a finding of liability on the breach of contract claim, finding that the award could only be sustained on the negligent misrepresentation claim. Virgin then appealed, seeking the full amount of damages awarded by the jury. The Supreme Court found that Virgin's negligent misrepresentation claim for money damages was capped by statute, therefore it was not entitled to the full amount of damages originally awarded by the jury. That cap does not apply to breach of contract, however, and because the trial court did not include findings with regard to liability on the breach of contract claim, the case was remanded for further proceedings.View "Victor Virgin Construction Corp. v. New Hampshire Dep't of Transportation" on Justia Law

by
Greco worked at MetroHealth, a county-owned health-care provider in Cleveland, from 1997 until 2009, supervising independent contractors who worked on MetroHealth construction projects, selecting contractors for small-scale no-bid maintenance projects, and authorizing payment for their work. Greco used his authority to facilitate a bribery scheme set up by his boss and Patel, the vice-president of a construction company. The participants became nervous and Greco took action to hide his involvement in the scheme, but Patel contacted the government and confessed; in exchange for a reduced sentence, Patel provided detailed information about the scheme. Greco was convicted of bribery and conspiracy to commit bribery involving programs receiving federal funds (18 U.S.C. 666(a)(1)(B) and 371), violation of and conspiracy to violate the Hobbs Act (18 U.S.C. 1951), making false tax returns (26 U.S.C. 7206(1)), and conspiracy to commit mail fraud (18 U.S.C. 1349) and was sentenced to 112 months’ imprisonment and required to pay $994,734.84 in restitution to MetroHealth. The Sixth Circuit affirmed, rejecting arguments that the court improperly applied a 12-level enhancement based on an erroneous loss calculation; improperly applied a two-level enhancement for obstruction of justice; and imposed a substantively unreasonable sentence. View "United States v. Greco" on Justia Law