Justia Government Contracts Opinion Summaries

Articles Posted in Energy, Oil & Gas Law
by
The Authority was formed under Ga. Code 46-4-82(a) to provide member municipalities with natural gas. It operates as a non-profit, distributing profits and losses to member municipalities: 64 in Georgia, two in Tennessee, 12 in other states. It pays its own operating expenses and judgments; it is exempt from state laws on financing and investment for state entities and has discretion over accumulation, investment, and management of its funds. It sets its governance rules; members elect leaders from among member municipalities. Smyrna, Tennessee has obtained gas from the Authority since 2000, using a pipeline that does not run through Georgia. The Authority entered a multi-year “hedge” contract for gas acquisition, setting price and volume through 2014, and passed the costs on. The market price of natural gas then fell due to increased hydraulic fracturing (fracking), but Smyrna was still paying the higher price. Smyrna sued for breach of contract, violations of the Tennessee Consumer Protection Act, breach of fiduciary duty, and unjust enrichment. The district court denied the Authority’s motion to dismiss based on sovereign immunity under Georgia law and the Eleventh Amendment. The Sixth Circuit affirmed, stating that the Authority’s claim that any entity referred to as a state “instrumentality” in a Georgia statute is entitled to state-law sovereign immunity “requires quite a stretch of the imagination.” View "Town of Smyrna, TN v. Mun. Gas Auth. of GA" on Justia Law

by
The 1987 Public Utilities Act, 220 ILCS 5/8-403.1, was intended to encourage development of power plants that convert solid waste to electricity. Local electric utilities were required to enter into 10-year agreements to purchase power from such plants designated as “qualified” by the Illinois Commerce Commission, at a rate exceeding that established by federal law. The state compensated electric utilities with a tax credit. A qualified facility was obliged to reimburse the state for tax credits its customers had claimed after it had repaid all of its capital costs for development and implementation. Many qualified facilities failed before they repaid their capital costs, so that Illinois never got its tax credit money back. The Act was amended in 2006, to establish a moratorium on new Qualified Facilities, provide additional grounds for disqualifying facilities from the subsidy, and expand the conditions that trigger a facility’s liability to repay electric utilities’ tax credits. The district court held that the amendment cannot be applied retroactively. The Seventh Circuit affirmed. The amendment does not clearly indicate that the new repayment conditions apply to monies received prior to the amendment and must be construed prospectively. View "Illinois v. Chiplease, Inc." on Justia Law

by
In 1983, the Nuclear Waste Policy Act established a plan for spent nuclear fuel (SNF) generated by nuclear power plants, 42 U.S.C. 10101–10270. The Act made utilities responsible for SNF storage until the U.S. Department of Energy (DOE) accepts the material. The Secretary of Energy entered into contracts with nuclear utilities to accept SNF in return for payment of fees. The Act provided that the Nuclear Regulatory Commission “shall not issue or renew a license” to any nuclear utility unless the utility has entered into a contract with DOE or DOE certifies ongoing negotiations. Nuclear utilities, including the owner of the Entergy nuclear power stations, entered into contracts and began making payments, which have continued. By 1994, DOE knew it would be unable to accept SNF by the Act’s January 31, 1998 deadline. In 1995, DOE issued a “Final Interpretation” that took the position that it did not have an unconditional obligation to begin performance on that date. Entergy sued, asserting that DOE’s partial breach caused it to incur additional costs for SNF storage. The claims court struck an unavoidable delay defense, based on a prior decision rejecting DOE’s argument that its failure was “unavoidable” under the contract. The Federal Circuit affirmed. View "Entergy Nuclear Fitzpatrick, LLC v. United States" on Justia Law

by
Kansas power companies suffered damages due to the government’s partial breach of the Standard Contract for Disposal of Spent Nuclear Fuel And/Or High-Level Radioactive Waste, authorized by the Nuclear Waste Policy Act of 1982, 42 U.S.C. 10101–10270. The Court of Federal Claims conducted a nine-day trial and awarded $10,632,454.83. The Federal Circuit affirmed in part. In determining the amount of damages, thel court correctly did not award damages for cost of capital and for the costs associated with researching alternative storage options for spent nuclear fuel and high level radioactive waste. The court also appropriately reduced the companies’ damages by the value of the benefit they received as a result of their mitigation activities. However, the court erred by not accepting the companies’ reasonable method for calculating overhead costs. View "KS Gas & Elec. Co. v. United States" on Justia Law

by
In 1983, the Nuclear Waste Policy Act, 42 U.S.C. 10101-10270, authorized the Department of Energy to contract with nuclear facilities for disposal of spent nuclear fuel and high level radioactive waste. The Standard Contract provided that rights and duties may be assignable with transfer of SNF title. Plaintiff entered into the Standard Contract in 1983 and sold its operation and SNF to ENVY in 2002, including assignment of the Standard Contract, except one payment obligation. Plaintiff transferred claims related to DOE defaults. As a result of DOE’s breach, ENVY built on-site dry-storage facilities. The Claims Court consolidated ENVY’s suit with plaintiff’s suit. The government admitted breach; the Claims Court awarded ENVY $34,895,467 (undisputed damages) and certain disputed damages. The Federal Circuit affirmed in part. Plaintiff validly assigned pre-existing claims; while partial assignment of rights and duties under the contract was not valid, the government waived objection. The assignment encompassed claims against the government. Legal and lobbying fees to secure Vermont approval for mitigation were foreseeable, but other expenses were not recoverable. ENVY failed to prove costs of disposing of contaminated material discovered due to the breach and its characterization of spent fuel moved to dry storage. ENVY is not entitled to recover cost of capital for funding mitigation, or Resource Code 19 payroll loader overhead costs, but may recover capital suspense loader overhead costs,.View "VT Yankee Nuclear Power Corp. v. United States" on Justia Law

by
In 1957 the Commonwealth constructed the Quehanna Wild Area Nuclear Site. Part of the site was donated to Pennsylvania State University. Until 1967 Penn State leased to a Lockheed predecessor, conducting work under Atomic Energy Commission contracts, involving Strontium-90, a radioactive isotope. The predecessor partially decontaminated. According to Lockheed, the Commonwealth was aware that Strontium-90 remained and could not be removed without dismantling the facility. In the 1990s, the Nuclear Regulatory Commission ordered the Commonwealth, the Pennsylvania Department of Environmental Protection, and the Department of Conservation and Natural Resources to decommission the facility. This cost more than $20 million. PADEP sued Lockheed under the Comprehensive Environmental Response, Compensation, and Liability Act, 42 U.S.C. 9607(a). Lockheed defended that the Commonwealth should recover less than its demand based on its own conduct and liability and the doctrines of unclean hands, estoppel, waiver, and laches. Lockheed also alleged that PADEP was liable under CERCLA as an owner-operator and as having arranged for or transported hazardous substances. The district court dismissed Lockheed’s third-party complaint, concluding that the Commonwealth and DCNR retained Eleventh Amendment immunity when PADEP filed a federal suit. The Third Circuit vacated with instructions to dismiss the third party complaint as moot, based on the sufficiency of Lockheed’s affirmative defenses. View "Commonwealth of PA Dep' of Envtl. Prot. v. Lockheed Martin Corp." on Justia Law

by
Power companies sought damages for the cost of storing spent nuclear fuel and high-level radioactive waste beyond when the government promised by contract to begin storing that waste in a permanent repository. In 2004, the claims court held a seven-week trial on damages. The Federal Circuit accepted its findings on foreseeability, reasonable certainty and the use of the substantial causal factor standard for causation purposes, and the determination that an award of Nuclear Waste Fund fees should be denied as premature, but remanded for application of the 1987 annual capacity report rate to damages claimed by the parties. On remand, the claims court accepted the fuel exchange model presented by plaintiffs’ expert and concluded that plaintiffs would not have built dry storage; two of the companies would not have reracked their storage pools under the 1987 ACR rate. The court found that, using fuel exchanges, plaintiffs would have emptied their wet storage facilities in the non-breach world within the first 10 years of DOE’s performance. The Federal Circuit reversed with respect to denial of claims for wet storage pool costs and NRC fees, which were within the mandate on remand, but otherwise affirmed. View "Yankee Atomic Elec. Co. v. United States" on Justia Law

by
In 1983, Congress enacted the Nuclear Waste Policy Act, 42 U.S.C. 10101-10270, authorizing the Department of Energy to enter into contracts with nuclear facilities for the disposal of spent nuclear fuel (SNF) and high-level radioactive waste (HLW). Congress mandated that, under the Standard Contract, DOE dispose of SNF and HLW beginning not later than January 31, 1998. In 1983, DOE entered into a Standard Contract with Consolidated Edison under which DOE agreed to accept SNF stored at the Indian Point facility. Following DOE’s breach, the Claims Court awarded two categories of damages: wet storage costs for continued operation of its Unit 1 spent fuel pool and regulatory fees paid to the U.S. Nuclear Regulatory Commission. The Federal Circuit reversed the awards, affirmed denial of damages for the cost of financing mitigation activities, but reversed denial of damages for indirect overhead costs associated with mitigation. The company had chosen to prioritize removal of Unit 2 SNF and Unit 1 material would not have been removed by the time at issue; the company did not establish that the breach caused an increase in fees to the NRC. View "Consol. Edison Co. of NY, Inc. v. United States" on Justia Law

by
During World War II, the U.S. contracted with oil companies for the production of aviation fuel, which resulted in production of hazardous waste. The waste was dumped at the California McColl site. Several decades later, the oil companies were held liable for cleanup costs under the Comprehensive Environmental Response, Compensation, and Liability Act, 42 U.S.C. 9601, and sought reimbursement from the government based on the contracts. The district court entered summary judgment on liability, finding that the contracts contained open ended indemnification agreements and encompassed costs for CERLCA cleanup, and awarded $87,344,345.70. The trial judge subsequently discovered that his wife had inherited 97.59 shares of stock in a parent to two of the oil companies. The judge ultimately vacated his summary judgment rulings; severed two companies from the suit and directed the clerk to reassign their claims to a different judge; reinstated his prior decisions with respect to two remaining companies; and entered judgment against the government ($68,849,505). The Federal Circuit vacated and remanded for reassignment to another judge. The judge was required to recuse himself under 28 U.S.C. 455(b)(4) and the error was not harmless.View "Shell Oil Co. v. United States" on Justia Law

by
In 2008 the district court calculated damages for the government's partial breach of the Standard Contract for disposal of spent nuclear fuel using the 1991 Annual Capacity Report and the duty of good faith and fair dealing. The Federal Circuit, having set the 1987 ACR as the appropriate acceptance rate for a causation analysis under the Standard Contract, remanded. On remand, the district court set the amount of damages at $89,004,415. The Federal Circuit affirmed, holding that the new judgment accounts for the proper causation times and principle. View "Pacific Gas & Elec. Co. v. United States" on Justia Law