Justia Government Contracts Opinion Summaries
Menominee Indian Tribe v. United States
The Tribe filed claims in 2005 against the Department for unpaid contract support costs that accrued from 1996 through 1998. At issue was whether the Tribe may sue under the doctrine of equitable tolling even though the statute of limitations has lapsed. The court concluded that the Tribe's claims were barred by the statute of limitations because the legal misunderstandings and tactical mistakes the Tribe identified did not amount to extraordinary circumstances justifying equitable tolling. Accordingly, the court affirmed the judgment of the district court. View "Menominee Indian Tribe v. United States" on Justia Law
Posted in:
Government Contracts, Native American Law
Folliard v. Government Acquisitions, Inc., et al.
Relator filed suit under the False Claims Act (FCA), 31 U.S.C. 3729-3733, alleging that the HP products Govplace sold to the federal government originated from non-designated countries, in violation of the Trade Agreements Act of 1979 (TAA), 19 U.S.C. 2501-2581. The court affirmed the district court's grant of summary judgment to Govplace, concluding that the district court properly exercised its discretion in managing discovery and that Govplace reasonably relied on Ingram Micro's certification. The court concluded that a contractor like Govplace is ordinarily entitled to rely on a supplier's certification that the product meets TAA requirements. In this case, Govplace has informed the GSA during multiple Contractor Administrator Visits that it relies on Ingram Micro's Program in representing that the country of origin information for the items listed in its GSA schedule is accurate, and GSA's Administrative Report Cards evaluating Govplace have all concluded that Govplace has complied with the TAA. View "Folliard v. Government Acquisitions, Inc., et al." on Justia Law
Posted in:
Government Contracts, International Trade
Kassotis v. Town of Fitzwilliam
Petitioner Wayne Kassotis appealed a Superior Court decision dismissing his complaint, arising from the nonrenewal of his employment contract to remain as the Town of Fitzwilliam's Chief of Police. Petitioner filed a complaint against the Town seeking, among other things, reinstatement as Chief of Police, damages, costs, and attorney’s fees, for the Town’s alleged failure to comply with RSA 105:2-a, which provided procedural protections to appointed chiefs of police who are "dismiss[ed]." The Town moved to dismiss, arguing that, "[b]ecause the Petitioner was not dismissed, RSA 105:2-a does not apply, and he fails to state a claim for relief." The trial court granted the Town’s motion on the basis that "the provisions of RSA 105:2-a are inapplicable to the [Town’s] decision not to renew the employment contract." Finding no reversible error, the Supreme Court affirmed.
View "Kassotis v. Town of Fitzwilliam" on Justia Law
Sheet Metal Workers Int’l. Ass’n v. Duncan
A contractor entered into a public works contract to modernize a building at a Santa Clara County community college. Will was the subcontractor for the heating, ventilation, and air conditioning (HVAC) work. The subcontract provided that the project was to be built according to the specifications of the prime contract. The subcontract and general contract did not specify whether Will was required to fabricate any material necessary to complete the HVAC work. The subcontract required Will to “pay not less than the [applicable prevailing wage] to all laborers, workmen, and mechanics employed by him at the project site.” California’s prevailing wage law generally requires that workers employed on public works be paid the local prevailing wage for work of a similar character. (Lab. Code,1771.) Since 1991, Will has fabricated materials at a permanent, offsite facility it operates in Hayward. An employee of Will complained to the Department of Industrial Relations, Division of Labor Standards Enforcement alleging he should have been paid prevailing wages for work related to the project, involving the fabrication of sheet metal at the Hayward facility. DLSE issued a civil wage and penalty assessment. The Department of Industrial Relations reversed, in favor of Will. The trial court reversed. The court of appeal held that offsite fabrication is not covered by the prevailing wage law if it takes place at a permanent, offsite manufacturing facility and the location and existence of that facility is determined wholly without regard to the particular public works project. View "Sheet Metal Workers Int'l. Ass'n v. Duncan" on Justia Law
United States v. Philip Morris USA Inc.
Appellant, the President and CEO of a tobacco company called Medallion, filed a qui tam action against Philip Morris, alleging that Philip Morris violated the False Claims Act (FCA), 31 U.S.C. 3729-3733, for failing to provide the government with "Most Favored Customer" pricing. The district court concluded that it lacked subject matter jurisdiction due to the FCA's public disclosure bar. The court concluded, however, that neither the contract term obligating Philip Morris to provide the government with Most Favored Customer pricing nor Philip Morris's fraudulent certifications that it complied was publicly disclosed. Accordingly, the court vacated and remanded for further proceedings. View "United States v. Philip Morris USA Inc." on Justia Law
Posted in:
Government Contracts
Stew Farm, Ltd. v. Natural Res. Conservation Serv.
The prior owner of the 300-acre STEW Farm in Pickaway County contracted with Watershed Management for construction of waterways and received a subsidy from the Natural Resources Conservation Service (NRCS), a USDA agency, 7 U.S.C. 6962. Kohli, an employee of the Pickaway County Soil and Water Conservation District supervised by NRCS, designed the waterways, and, after certified that they were designed and constructed properly. NRCS also certified the waterways, which allowed the owner to receive the federal reimbursement. The owner failed to pay Watershed, claiming that there was a ridge at the edge of the grass waterways that prevented proper draining. In 2009, Watershed sued for breach of contract; the owner counterclaimed for breach of contract and breach of warranty. A state court granted summary judgment against the owner for failure to prove damages. The new owner then filed a federal suit. The district court dismissed, reasoning, as to NRCS, that STEW Farm had not identified a separate source of federal substantive law and failed to establish a waiver of sovereign immunity because there are no “clear guidelines” which show that the NRCS actions were not committed to agency discretion. As to Watershed, the court concluded that there was no federal cause of action nor did the state claims implicate significant federal issues. As to PCSWCD, STEW Farm alleged only state-law claims that did not implicate significant federal issues. As to PCSWCD and Kohli, the claims were time barred under Ohio’s two-year statute of limitations. The Seventh Circuit affirmed. View "Stew Farm, Ltd. v. Natural Res. Conservation Serv." on Justia Law
Stevens & Wilkinson of South Carolina, Inc. v. City of Columbia
The respondents, two developers and an architectural firm, Stevens & Wilkinson of South Carolina, Inc. (S&W), entered into a Memorandum of Understanding (MOU) with the City of Columbia as part of a larger project team to develop a publicly-funded hotel for the Columbia Metropolitan Convention Center. The City eventually abandoned its plan under the MOU, and the respondents brought suit on several causes of action including breach of contract and equitable relief. The City moved for summary judgment arguing the MOU was not a contract and therefore the contract claims failed. The circuit court agreed and, rejecting the equitable claims as well, granted summary judgment in favor of the City. The respondents appealed and the court of appeals affirmed in part and reversed in part. The Supreme Court reversed. Because the MOU was comprised of agreements to execute further agreements, there was no meeting of the minds on numerous material terms which had not yet been defined. Accordingly, the court of appeals was reversed with respect to that portion of the court's judgment; the Supreme Court held the MOU was unenforceable as a matter of law. The Supreme Court agreed with the circuit court and reinstated its judgment in favor of the City.
View "Stevens & Wilkinson of South Carolina, Inc. v. City of Columbia" on Justia Law
Stevens & Wilkinson of South Carolina, Inc. v. City of Columbia
In April 2003, the City of Columbia entered into a Memorandum of Understanding (MOU) with Stevens & Wilkinson of South Carolina, Inc. (S&W) and several other parties, to develop a publicly-funded hotel adjacent to the Columbia Metropolitan Convention Center. As architect, S&W was to complete sufficient preliminary design work to determine a guaranteed maximum price for the project, which would be used by the City to obtain municipal bond funding to cover the cost of the hotel. Pursuant to the MOU, the construction company was to pay S&W directly. On June 26, 2003, the City received a letter stating S&W would complete its preliminary design on July 10, 2003, and would then stop working until the bond financing for the hotel was finalized. Realizing this could delay the start of construction, S&W offered to continue working the remaining ninety days until the anticipated bond closing date of October 13, 2003, but required assurance it would be compensated for the work it performed during this time frame. It provided an estimate requiring $650,000 and $75,000 per week after that. On July 30, the City approved "$650,000 for interim architectural design services for a period of 90 days prior to bond closing." The bond closing did not occur as scheduled, but S&W nevertheless continued to work. S&W submitted an invoice to the City for $697,084.79 for work that took place from July 10 to December 15, 2003. By letter dated December 17, 2003, S&W informed the construction company that the City had voted that day "to advance [$705,000.000] to the design team for design services and expenses. Because under the MOU the construction company was to pay S&W, not the City, the construction company agreed to reimburse the City for the funds paid to S&W after the bond closing. The City paid S&W's invoice. S&W continued to work on the project, but in March 2004, the City abandoned its plans under the MOU and ended its relationship with S&W. S&W received no further compensation and sued the City for breach of contract under the MOU and the July 2003 agreement. The City argued there was no separate agreement and the payment of interim fees was merely an advance on fees under the MOU and furthermore, the MOU provided that S&W was to be paid by the construction company, not the City. The trial court granted partial summary judgment in favor of S&W, finding a contract existed between it and the City. On certiorari, the City conceded a contract exists, but argued the contract terms have been satisfied. The Supreme Court found the City's arguments were unpreserved and affirmed as modified.
View "Stevens & Wilkinson of South Carolina, Inc. v. City of Columbia" on Justia Law
Rush Univ. Med. Ctr v. Sebelius
To compensate teaching hospitals for the extra financial burden of providing training, the Medicare program provides additional reimbursement for expenses beyond the immediate costs of patient care, including for “indirect medical education” (IME) costs to account for the time medical interns and residents spend in ways that enhance their ability to provide patient care but that are not connected to the treatment of any particular patient, 42 U.S.C. 1395ww(d)(5)(B)(ii). The district court held that time spent by interns and residents in research activities wholly unrelated to the diagnosis or treatment of patients could be counted as part of this indirect-education time and that Rush University Medical Center, was entitled to Medicare reimbursements for these activities between the years 1983 and 2001. The Seventh Circuit reversed and remanded, noting that the Secretary of Health and Human Services has interpreted the Medicare Act consistently since 1983 to exclude pure research activities from compensable IME costs. Congress codified this exclusion for Fiscal Years 2001 onward in the Patient Protection and Affordable Care Act of 2010, but explicitly declined to lay down a rule for the years 1983 to 2001. The Secretary has now promulgated a regulation excluding pure research from the IME cost calculation for all years since 1983. View "Rush Univ. Med. Ctr v. Sebelius" on Justia Law
United States v. Banks
Defendants-Appellants David Banks, Kendrick Barnes, Demetrius Harper, Clinton Stewart, Gary Walker, and David Zirpolo were convicted following a jury trial on multiple counts of mail fraud and wire fraud, and conspiracy to commit mail fraud and wire fraud. Defendants contacted numerous staffing agencies to “assist in providing temporary services. Witnesses from multiple staffing companies testified that a Defendant (or someone acting as Defendants’ agent) approached them and expressed the desire for "payrolling" services. The staffing-company witnesses testified that they were induced into believing that Defendants’ companies were either doing business with major law-enforcement agencies or were on the verge of selling a specialized software to these agencies. These witnesses testified that Defendants (or Defendants’ agents) assured them that this alleged law-enforcement business would enable Defendants’ companies to pay the staffing companies’ invoices, and, critically, that they relied on these representations in choosing to do business with Defendants. Trial testimony from representatives of the law-enforcement agencies with whom Defendants claimed to be doing business revealed the falsity of Defendants’ representations to the staffing companies. When questioned about their failure to pay the staffing companies’ invoices, Defendants gave false assurances that payment would be forthcoming, and they continued to imply that they were doing business with large government law enforcement agencies. In the end, forty-two different staffing companies were left with outstanding invoices totaling in excess of $5,000,000, which could not be submitted to the government agencies, which had no business relationship with Defendants’ companies. Defendants were sentenced to terms of imprisonment ranging from 87 to 135 months. Defendants argued on appeal to the Tenth Circuit: (1) their right to a speedy trial was violated when the district court granted multiple continuances of the trial date (at Defendants’ request); (2) the district court compelled co-Defendant Barnes to testify in violation of his Fifth Amendment privilege against self-incrimination and failed to give a proper curative instruction; (3) the district court abused its discretion in excluding the testimony of two witnesses Defendants sought to call at trial; and (4) the cumulative effect of the district court’s otherwise harmless errors prejudiced them and required reversal. Finding no reversible error, the Tenth Circuit affirmed.
View "United States v. Banks" on Justia Law